CRIP/WORKS/RDA/NCB/300

Reconstruction of Nadimale Bridge ( No. 4/1) on Dehiwala ??? Maharagama Road (B094)
??? Contractor : Sathuta Builders
??? Contract Value (Without VAT) : 188,125,551.90
??? Date of Commencement : 26th November 2014
??? Original Date of Completion : 25th February 2016
??? E O T Granted : 1st March 2017
??? Revised Date of Completion : 31st August 2017